Earned
value management (EVM), or Earned value project/performance management (EVPM)
is a project management technique for measuring project performance and
progress in an objective manner.
Because
EVM has the ability to combine measurements of :
1.scope
2.schedule
3.and
cost,
in a
single integrated system, Earned Value Management is able to provide accurate
forecasts of project performance problems, which is an important contribution
for project management.
Early
EVM research showed that the areas of planning and control are significantly
impacted by its use; and similarly, using the methodology improves both scope
definition as well as the analysis of overall project performance. More recent
research studies have shown that the principles of EVM are positive predictors
of project success. Popularity of EVM has grown significantly in recent
years beyond government contracting, in which sector its importance continues
to rise (e.g., recent new DFAR rules), in part because EVM can also
surface in and help substantiate contract disputes
Introduction
to EVM
Essential
features of any EVM implementation include
1.a
project plan that identifies work to be accomplished,
2.a
valuation of planned work, called Planned Value (PV) or Budgeted Cost of Work
Scheduled (BCWS), and
3.pre-defined
“earning rules” (also called metrics) to quantify the accomplishment of work,
called Earned Value (EV) or Budgeted Cost of Work Performed (BCWP).
EVM
implementations for large or complex projects include many more features, such
as indicators and forecasts of cost performance (over budget or under budget)
and schedule performance (behind schedule or ahead of schedule). However, the
most basic requirement of an EVM system is that it quantifies progress using PV
and EV.
Project
tracking without EVM
It is
helpful to see an example of project tracking that does not include earned
value performance management. Consider a project that has been planned in
detail, including a time-phased spend plan for all elements of work. Figure 1
shows the cumulative budget (cost) for this project as a function of time (the
blue line, labeled PV). It also shows the cumulative actual cost of the project
(red line) through week 8. To those unfamiliar with EVM, it might appear that
this project was over budget through week 4 and then under budget from week 6
through week 8. However, what is missing from this chart is any understanding
of how much work has been accomplished during the project. If the project were actually
completed at week 8, then the project would actually be well under budget and
well ahead of schedule. If, on the other hand, the project is only 10% complete
at week 8, the project is significantly over budget and behind schedule. A
method is needed to measure technical performance objectively and
quantitatively, and that is what EVM accomplishes.
Project
tracking with EVM
Consider
the same project, except this time the project plan includes pre-defined
methods of quantifying the accomplishment of work. At the end of each week, the
project manager identifies every detailed element of work that has been
completed, and sums the PV for each of these completed elements. Earned value
may be accumulated monthly, weekly, or as progress is made.
Earned
value (EV)
Figure
2 shows the EV curve (in green) along with the PV curve from Figure 1. The
chart indicates that technical performance (i.e., progress) started more
rapidly than planned, but slowed significantly and fell behind schedule at week
7 and 8. This chart illustrates the schedule performance aspect of EVM. It is
complementary to critical path or critical chain schedule management.
Figure 3 shows the same EV curve (green) with
the actual cost data from Figure 1 (in red). It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1.
History
EVM emerged as a financial analysis specialty in United States Government programs in the 1960s, but it has since become a significant branch of project management and cost engineering. Project management research investigating the contribution of EVM to project success suggests a moderately strong positive relationship.[8] Implementations of EVM can be scaled to fit projects of all sizes and complexities.
The
genesis of EVM occurred in industrial manufacturing at the turn of the 20th
century, based largely on the principle of "earned time" popularized by
Frank and Lillian Gilbreth, but the concept took root in the United States
Department of Defense in the 1960s. The original concept was called PERT/COST,
but it was considered overly burdensome (not very adaptable) by contractors who
were mandated to use it, and many variations of it began to proliferate among
various procurement programs. In 1967, the DoD established a criterion-based
approach, using a set of 35 criteria, called the Cost/Schedule Control Systems
Criteria (C/SCSC). In 1970s and early 1980s, a subculture of C/SCSC analysis
grew, but the technique was often ignored or even actively resisted by project
managers in both government and industry. C/SCSC was often considered a
financial control tool that could be delegated to analytical specialists.
In the
late 1980s and early 1990s, EVM emerged as a project management methodology to
be understood and used by managers and executives, not just EVM specialists. In
1989, EVM leadership was elevated to the Undersecretary of Defense for
Acquisition, thus making EVM an essential element of program management and
procurement. In 1991, Secretary of Defense Dick Cheney canceled the Navy A-12
Avenger II Program because of performance problems detected by EVM. This
demonstrated conclusively that EVM mattered to secretary-level leadership. In
the 1990s, many U.S. Government regulations were eliminated or streamlined.
However, EVM not only survived the acquisition reform movement, but became
strongly associated with the acquisition reform movement itself. Most notably,
from 1995 to 1998, ownership of EVM criteria (reduced to 32) was transferred to
industry by adoption of ANSI EIA 748-A standard.
The
use of EVM quickly expanded beyond the U.S. Department of Defense. It was
adopted by the National Aeronautics and Space Administration, United States
Department of Energy and other technology-related agencies. Many industrialized
nations also began to utilize EVM in their own procurement programs. An
overview of EVM was included in first PMBOK Guide in 1987 and expanded in
subsequent editions. The construction industry was an early commercial adopter
of EVM. Closer integration of EVM with the practice of project management
accelerated in the 1990s. In 1999, the Performance Management Association
merged with the Project Management Institute (PMI) to become PMI’s first
college, the College of Performance Management. The United States Office of
Management and Budget began to mandate the use of EVM across all government
agencies, and, for the first time, for certain internally managed projects (not
just for contractors). EVM also received greater attention by publicly traded
companies in response to the Sarbanes-Oxley Act of 2002.
In
Australia EVM has been codified as standards AS 4817-2003 and AS 4817-2006.
Scaling
EVM from simple to advanced implementations
The
foundational principle of EVM, mentioned above, does not depend on the size or
complexity of the project. However, the implementations of EVM can vary
significantly depending on the circumstances. In many cases, organizations
establish an all-or-nothing threshold; projects above the threshold require a
full-featured (complex) EVM system and projects below the threshold are
exempted. Another approach that is gaining favor is to scale EVM implementation
according to the project at hand and skill level of the project team
Simple
implementations (emphasizing only technical performance)
There
are many more small and simple projects than there are large and complex ones,
yet historically only the largest and most complex have enjoyed the benefits of
EVM. Still, lightweight implementations of EVM are achievable by any person who
has basic spreadsheet skills. In fact, spreadsheet implementations are an
excellent way to learn basic EVM skills.
The
first step is to define the work. This is typically done in a hierarchical
arrangement called a work breakdown structure (WBS) although the simplest
projects may use a simple list of tasks. In either case, it is important that
the WBS or list be comprehensive. It is also important that the elements be
mutually exclusive, so that work is easily categorized in one and only one
element of work. The most detailed elements of a WBS hierarchy (or the items in
a list) are called activities (or tasks).
The
second step is to assign a value, called planned value (PV), to each activity.
For large projects, PV is almost always an allocation of the total project
budget, and may be in units of currency (e.g., dollars or euros) or in labor
hours, or both. However, in very simple projects, each activity may be assigned
a weighted “point value" which might not be a budget number. Assigning
weighted values and achieving consensus on all PV quantities yields an
important benefit of EVM, because it exposes misunderstandings and miscommunications
about the scope of the project, and resolving these differences should always
occur as early as possible. Some terminal elements can not be known (planned)
in great detail in advance, and that is expected, because they can be further
refined at a later time.
The
third step is to define “earning rules” for each activity. The simplest method
is to apply just one earning rule, such as the 0/100 rule, to all activities.
Using the 0/100 rule, no credit is earned for an element of work until it is
finished. A related rule is called the 50/50 rule, which means 50% credit is
earned when an element of work is started, and the remaining 50% is earned upon
completion. Other fixed earning rules such as a 25/75 rule or 20/80 rule are
gaining favor, because they assign more weight to finishing work than for
starting it, but they also motivate the project team to identify when an
element of work is started, which can improve awareness of work-in-progress.
These simple earning rules work well for small or simple projects because
generally each activity tends to be fairly short in duration.
These
initial three steps define the minimal amount of planning for simplified EVM.
The final step is to execute the project according to the plan and measure
progress. When activities are started or finished, EV is accumulated according
to the earning rule. This is typically done at regular intervals (e.g., weekly
or monthly), but there is no reason why EV cannot be accumulated in near
real-time, when work elements are started/completed. In fact, waiting to update
EV only once per month (simply because that is when cost data are available)
only detracts from a primary benefit of using EVM, which is to create a
technical performance scoreboard for the project team.
In a
lightweight implementation such as described here, the project manager has not
accumulated cost nor defined a detailed project schedule network (i.e., using a
critical path or critical chain methodology). While such omissions are
inappropriate for managing large projects, they are a common and reasonable
occurrence in many very small or simple projects. Any project can benefit from
using EV alone as a real-time score of progress. One useful result of this very
simple approach (without schedule models and actual cost accumulation) is to
compare EV curves of similar projects, as illustrated in Figure 5. In this
example, the progress of three residential construction projects are compared
by aligning the starting dates. If these three home construction projects were
measured with the same PV valuations, the relative schedule performance of the
projects can be easily compared.
Intermediate
implementations (integrating technical and schedule performance)
In
many projects, schedule performance (completing the work on time) is equal in
importance to technical performance. For example, some new product development
projects place a high premium on finishing quickly. It is not that cost is
unimportant, but finishing the work later than a competitor may cost a great
deal more in lost market share. It is likely that these kinds of projects will
not use the lightweight version of EVM described in the previous section,
because there is no planned timescale for measuring schedule performance. A
second layer of EVM skill can be very helpful in managing the schedule performance
of these “intermediate” projects. The project manager may employ a critical
path or critical chain to build a project schedule model. As in the lightweight
implementation, the project manager must define the work comprehensively,
typically in a WBS hierarchy. He/she will construct a project schedule model
that describes the precedence links between elements of work. This schedule
model can then be used to develop the PV curve (or baseline), as shown in
Figure 2.
It
should be noted that measuring schedule performance using EVM does not replace
the need to understand schedule performance versus the project's schedule model
(precedence network). However, EVM schedule performance, as illustrated in
Figure 2 provides an additional indicator — one that can be communicated in a
single chart. Although it is theoretically possible that detailed schedule
analysis will yield different conclusions than broad schedule analysis, in
practice there tends to be a high correlation between the two. Although EVM schedule
measurements are not necessarily conclusive, they provide useful diagnostic
information.
Although
such intermediate implementations do not require units of currency (e.g.,
dollars), it is common practice to use budgeted dollars as the scale for PV and
EV. It is also common practice to track labor hours in parallel with currency.
The following EVM formulas are for schedule management, and do not require
accumulation of actual cost (AC). This is important because it is common in
small and intermediate size projects for true costs to be unknown or
unavailable.
Schedule variance (SV)
SV
greater than 0 is good (ahead of schedule). The SV will be 0 at project
completion because then all of the planned values will have been earned.
Schedule
performance index (SPI)
SPI
greater than 1 is good (ahead of schedule).
Advanced
implementations (integrating cost, schedule and technical performance)
In
addition to managing technical and schedule performance, large and complex
projects require that cost performance be monitored and reviewed at regular
intervals. To measure cost performance, planned value (or BCWS - Budgeted Cost
of Work Scheduled) and earned value (or BCWP - Budgeted Cost of Work Performed)
must be in units of currency (the same units that actual costs are measured.)
In large implementations, the planned value curve is commonly called a
Performance Measurement Baseline (PMB) and may be arranged in control accounts,
summary-level planning packages, planning packages and work packages. In large
projects, establishing control accounts is the primary method of delegating
responsibility and authority to various parts of the performing organization.
Control accounts are cells of a responsibility assignment (RACI) matrix, which
is intersection of the project WBS and the organizational breakdown structure
(OBS). Control accounts are assigned to Control Account Managers (CAMs). Large
projects require more elaborate processes for controlling baseline revisions,
more thorough integration with subcontractor EVM systems, and more elaborate
management of procured materials.
In the
United States, the primary standard for full-featured EVM systems is the
ANSI/EIA-748A standard, published in May 1998 and reaffirmed in August 2002.
The standard defines 32 criteria for full-featured EVM system compliance. As of
the year 2007, a draft of ANSI/EIA-748B, a revision to the original is
available from ANSI. Other countries have established similar standards.
In
addition to using BCWS and BCWP, prior to 1998 implementations often use the
term Actual Cost of Work Performed (ACWP) instead of AC. Additional acronyms
and formulas include:
Budget
at completion (BAC): The total planned value (PV or BCWS) at the end of the
project. If a project has a Management Reserve (MR), it is typically not
included in the BAC, and respectively, in the Performance Measurement Baseline.
Cost
variance (CV)
CV
greater than 0 is good (under budget).
Cost
Performance Index (CPI)
CPI
greater than 1 is good (under budget):
< 1
means that the cost of completing the work is higher than planned (bad);
= 1
means that the cost of completing the work is right on plan (good);
> 1
means that the cost of completing the work is less than planned (good or
sometimes bad).
Having
a CPI that is very high (in some cases, very high is only 1.2) may mean that
the plan was too conservative, and thus a very high number may in fact not be
good, as the CPI is being measured against a poor baseline. Management or the
customer may be upset with the planners as an overly conservative baseline ties
up available funds for other purposes, and the baseline is also used for
manpower planning.
Estimate
at completion (EAC)
EAC is
the manager's projection of total cost of the project at completion.
Estimate
to complete (ETC)
ETC is
the estimate to complete the remaining work of the project.
To-complete
performance index (TCPI)
The
TCPI provides a projection of the anticipated performance required to achieve
either the BAC or the EAC. TCPI indicates the future required cost efficiency
needed to achieve a target BAC (Budget At Complete) or EAC (Estimate At
Complete). Any significant difference between CPI, the cost performance to
date, and the TCPI, the cost performance needed to meet the BAC or the EAC,
should be accounted for by management in their forecast of the final cost.
For
the TCPI based on BAC (describing the performance required to meet the original
BAC budgeted total):
or for
the TCPI based on EAC (describing the performance required to meet a new,
revised budget total EAC):
Independent
estimate at completion (IEAC)
The
IEAC is a metric to project total cost using the performance to date to project
overall performance. This can be compared to the EAC, which is the manager's
projection.
Limitations
EVM
has no provision to measure project quality, so it is possible for EVM to
indicate a project is under budget, ahead of schedule and scope fully executed,
but still have unhappy clients and ultimately unsuccessful results. In other
words, EVM is only one tool in the project manager's toolbox.
Because
EVM requires quantification of a project plan, it is often perceived to be
inapplicable to discovery-driven or Agile software development projects. For
example, it may be impossible to plan certain research projects far in advance,
because research itself uncovers some opportunities (research paths) and
actively eliminates others. However, another school of thought holds that all
work can be planned, even if in weekly timeboxes or other short increments. Thus,
the challenge is to create agile or discovery-driven implementations of the EVM
principle, and not simply to reject the notion of measuring technical
performance objectively. (See the lightweight implementation for small
projects, described above). Applying EVM in fast-changing work environments is,
in fact, an area of project management research.
Traditional
EVM is not intended for non-discrete (continuous) effort. In traditional EVM
standards, non-discrete effort is called “level of effort" (LOE). If a
project plan contains a significant portion of LOE, and the LOE is intermixed
with discrete effort, EVM results will be contaminated.[13] This is another
area of EVM research.
Traditional
definitions of EVM typically assume that project accounting and project network
schedule management are prerequisites to achieving any benefit from EVM. Many
small projects don't satisfy either of these prerequisites, but they too can
benefit from EVM, as described for simple implementations, above. Other
projects can be planned with a project network, but do not have access to true
and timely actual cost data. In practice, the collection of true and timely
actual cost data can be the most difficult aspect of EVM. Such projects can
benefit from EVM, as described for intermediate implementations, above, and
Earned Schedule.
As a
means of overcoming objections to EVM's lack of connection to qualitative
performance issues, the Naval Air Systems Command (NAVAIR) PEO(A) organization
initiated a project in the late 1990s to integrate true technical achievement
into EVM projections by utilizing risk profiles. These risk profiles anticipate
opportunities that may be revealed and possibly be exploited as development and
testing proceeds. The published research resulted in a Technical Performance
Management (TPM) methodology and software application that is still used by
many DoD agencies in informing EVM estimates with technical achievement.[14]
The research was peer-reviewed and was the recipient of the Defense Acquisition
University Acquisition Research Symposium 1997 Acker Award for excellence in
the exchange of information in the field of acquisition research.











No comments:
Post a Comment